Location:
Bloomington, MN
Bloomington, MN
Client:
McGough Construction
Scope:
Demolition, Earthwork, Site Utilities, soil retention
- 55,000 cy of granular soils export
- 16,000 cy of cut and fill on site
- 70,000 SF of parking ramp area prepped
- 10,000 SF of soil retention installed
- 1700 LF of water main installed vi. 1400 LF of sanitary sewer installed
- 1500 LF of storm water piping installed
- 2 large stormwater infiltration systems installed